Project Name:
Nuneaton
Following the disconnection and removal of the high bay racking in their existing over 30m tall building at Saputo Dairy – Nuneaton. A new state of the art cheese process plant was formed within the existing structure.
AM Fire Systems remit was to disconnect the current racking sprinklers, replace 800+ high level sprinklers due to their age followed by the installation of over 1,000 new sprinklers and pipework above the clean room ceiling to protect the new clean rooms, under stainless steel platforms and ductwork.
The design standards adopted was BS EN 12845 high hazard process with varying densities ranging from 10mm to 17.5mm fed from a new 200mm sprinkler control valve utilising the existing water supplies.